Metropole Pte Ltd v Designshop Pte Ltd
Jurisdiction | Singapore |
Judge | Vinodh Coomaraswamy J |
Judgment Date | 07 March 2017 |
Neutral Citation | [2017] SGHC 45 |
Plaintiff Counsel | Tan Tian Luh and Tan Xian Ying (Chancery Law Corporation) |
Docket Number | Originating Summons No 384 of 2016 |
Date | 07 March 2017 |
Hearing Date | 07 July 2016 |
Subject Matter | Terms,Statutes and regulations,Building and Construction Law,Building and Construction Industry Security of Payment Act |
Published date | 29 December 2017 |
Defendant Counsel | Samuel Chacko and Christopher Yeo (Legis Point LLC) |
Court | High Court (Singapore) |
Citation | [2017] SGHC 45 |
Year | 2017 |
This is an application by Metropole Private Limited (“Metropole”) to set aside an adjudication determination dated 1 April 2016 on a number of grounds.1 The respondent is Designshop Pte Ltd (“DPL”).
I have rejected each of Metropole’s grounds and dismissed the application. Metropole has appealed to the Court of Appeal. I therefore now give my reasons.
Background facts The parties’ contractIn June 2009, Metropole engaged Designshop.Architects LLP (“the LLP”) to provide architectural services in relation to a project to carry out additions and alternations to seven shophouses at Sims Avenue.2 Mr Lim Hong Kian (“Lim”), Ms Joy Chew Chia Pow (“Chew”) and Ms Yeo Pei Shan were partners of the LLP.
Metropole and the LLP contracted on the terms set out in the Singapore Institute of Architects’ standard form Conditions of Appointment and Architects Services and Mode of Payment (“the SIA terms”).3 Lim was the “qualified person” designated for the project for the purposes of the Building Control Act (Cap 29, 1999 Rev Ed) (“the BCA”). He was also the architect in charge of and responsible for the project.4
The parties’ contract divided the work which the LLP was to undertake in the project into stages identified by letters of the alphabet. The contract also stipulated the fee for each stage, expressed as a percentage of the fees for basic services, or the “Construction Cost”. Clause 2.3(3) of the parties’ contract – identical to cl 2.3(3) of the SIA terms5 – obliged Metropole, upon termination of the contract, to pay the LLP a minimum of two-thirds of the fee for a particular stage of work if the LLP had carried out any work at all for that stage, even in part.6 To be precise, the clause provides that even if DPL renders only partial services for a particular stage, DPL shall nonetheless be “entitled to charge commensurate with the service provided but not less than two-third (2/3) of the fee for the incomplete stage”.7
In January 2012, the three partners of the LLP decided to incorporate their architectural practice using DPL as the corporate vehicle. They applied to and obtained the necessary approval from the Board of Architects. DPL then took over the performance of all ongoing projects handled by the LLP, including Metropole’s project.8 Lim remained the designated “qualified person” and the architect in charge of and responsible for the project.
In January 2016, Lim left DPL.9 It was not an amicable parting. The day after Lim left DPL, Metropole instructed DPL in writing that DPL was not to take any further steps or actions or incur any further costs or disbursements for the project. It also gave notice to DPL on 11 February 2016 terminating the parties’ contract.10
The payment claim On 17 February 2016, DPL issued and served on Metropole a payment claim in the sum of $453,948.43.11 The payment claim set out a breakdown of this sum. The sum included fees for the stages of work which DPL believed were completed (
On 24 February 2016, Metropole served on DPL its payment response.14 In it, Metropole disputed DPL’s claim of $453,948.43 and, in particular, disputed DPL’s entitlement to rely on cl 2.3(3). Metropole’s position was that that clause entitled DPL to two-thirds of the fee for a particular stage only if DPL had rendered
The payment response also asserted Metropole’s belief that it had contracted personally with Lim and not with DPL.17 It noted that Lim left DPL in January 2016 and stated that the contract was then only at the stage of tender evaluation.18 It added that “[n]o tender [had] been awarded to any contractors, no submission [had] been made yet for Building Plan clearance and it [had] not reached [the] stage for Building Plan approval submission.”19
On 3 March 2016, DPL responded by letter to Metropole’s payment response and set out its position on the issues raised.20 DPL claimed
Metropole did not respond to DPL’s letter dated 3 March 2016.
On 7 March 2016, DPL gave notice to Metropole under s 12(2) of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”). The notice claimed a reduced sum of $262,765.85.24 The reduction had come about because Metropole had, after receiving DPL’s payment claim, paid DPL $191,182.59.25
The adjudicationOn 9 March 2016, DPL made its adjudication application.26
On 17 March 2016, Metropole lodged its adjudication response. The issues which the adjudication response raised included the following:
An adjudication conference took place on 29 March 2016. The parties presented their cases to the adjudicator.31 He issued his determination on 1 April 2016.32 The determination may be summarised as follows:
On 15 April 2016, Metropole applied to set aside the adjudication determination.39
The events of 31 March 2016I move back in the chronology to examine the events of 31 March 2016, as they are of particular importance. This date was two days after the adjudication conference and one day before the adjudicator was obliged to issue his determination.
At about 10.20am on 31 March 2016, the adjudicator telephoned DPL’s solicitors to ask two questions.40 First, the adjudicator asked whether DPL had issued a second tender evaluation report. Second, the adjudicator asked how DPL had derived the “Construction Cost” of $7,116,500 as stated in the payment claim, if there was no second tender evaluation report. He asked DPL to respond to the two questions by email copied to Metropole.
The cause of the adjudicator’s confusion was that the first tender evaluation report indicated that the lowest quotation then available,41 submitted by Poplar Construction Pte Ltd (“Poplar”), was for a sum of $7,318,000,42 and not for the sum of $7,116,500 which had been common ground between the parties in the adjudication.
DPL’s solicitors set out and answered the adjudicator’s two questions by an email sent to the adjudicator at 12.36 pm the same day,...
To continue reading
Request your trial- Leap Modulation Sdn Bhd v PCP Construction Sdn Bhd (and Another Appeal)
-
BOI v BOJ
...at [53]; AMZ v AXX [2016] 1 SLR 549 at [94]; TOW v TOV [2017] 3 SLR 725 (“TOW v TOV”) at [31]; Metropole Pte Ltd v Designshop Pte Ltd [2017] 4 SLR 277 at [47]; and UES Holdings Pte Ltd v KH Foges Pte Ltd [2018] 3 SLR 648 at [29]). We touched on this issue at [92] above by referring to [40] ......
-
Bintai Kindenko Pte Ltd v Samsung C&T Corp
...by the requirement for an adjudicator to receive and consider the submissions of both parties: Metropole Pte Ltd v Designshop Pte Ltd [2017] 4 SLR 277 (“Metropole”) at [57], citing AM Associates at [25]; the second was on the basis of its contention that the fair hearing rule requires an ad......
-
CMC Ravenna Singapore Branch v CGW Construction & Engineering (S) Pte Ltd
...the dispute: UES Holdings Pte Ltd v KH Foges Pte Ltd [2017] SGHC 114 (“Foges”) at [28], quoting Metropole Pte Ltd v Designshop Pte Ltd [2017] SGHC 45 at [46]. Invalid appointment of adjudicator and non-compliance with important statutory A court also has the power to set aside an adjudicati......