Marty Ltd v Hualon Corporation (Malaysia) Sdn Bhd (receiver and manager appointed)
Jurisdiction | Singapore |
Judge | Sundaresh Menon CJ,Judith Prakash JA,Tay Yong Kwang JA |
Judgment Date | 10 October 2018 |
Neutral Citation | [2018] SGCA 63 |
Year | 2018 |
Date | 10 October 2018 |
Published date | 21 November 2018 |
Hearing Date | 06 July 2018 |
Plaintiff Counsel | Philip Jeyaretnam SC, Paras Manohar Lalwani, Chua Weilin and Tan Ting Wei (Dentons Rodyk & Davidson LLP) |
Defendant Counsel | Yogarajah Yoga Sharmini, Subashini d/o Narayanasamy and Kannan s/o Balakrishnan (Haridass Ho & Partners) |
Court | Court of Appeal (Singapore) |
Citation | [2018] SGCA 63 |
Docket Number | Civil Appeal No 175 of 2017 |
This appeal examines the circumstances in which a party to an arbitration agreement who commences court proceedings may be held to have lost its right to refer the same disputes to arbitration and the legal basis which would justify such a holding.
The parties before us are parties to an on-going arbitration. The appellant challenged the jurisdiction of the arbitrator on the basis that the respondent had, by its actions in a foreign court, waived its right to submit its disputes with the appellant to arbitration in Singapore or had repudiated the arbitration agreement. Having lost its jurisdictional challenge before the arbitral tribunal, the appellant filed an application pursuant to s 10(3) of the International Arbitration Act (Cap 143A, 2002 Rev Ed), challenging the tribunal’s decision. The High Court Judge (“the Judge”) agreed with the tribunal and dismissed the application with costs.
Before us the appellant appeals against the Judge’s decision on the following grounds:
Hualon Corporation (Malaysia) Sdn Bhd, a Malaysian company that was incorporated in 1989, is the respondent in this appeal. It was put into receivership in November 2006. Prior thereto its directors were two brothers, namely, Mr Oung Da Ming and Mr Oung Yu-Ming (collectively “the Oung brothers”). The Oung brothers were substantial shareholders in the respondent. They were also shareholders in three related companies: Hualon Chemical and Textile Co Ltd (“Hualon Chemical”), Hualon Corporation Taiwan which itself was a substantial shareholder in the respondent, and E-Hsin International Corporation (“E-Hsin”).
In 1993, the respondent incorporated a company in Vietnam known as Hualon Corporation Vietnam as its wholly-owned subsidiary (“the Vietnam Subsidiary”). The Vietnam Subsidiary was governed by its company charter issued on 30 December 1993. Mr Oung Da Ming was its chairman.
In June 1999, the Vietnam Subsidiary issued shares to Hualon Chemical and E-Hsin (“the 1999 transfers”) and, as a result, was no longer wholly owned by the respondent. The Oung brothers, as the then-directors of the respondent, procured the 1999 transfers.
Starting in late 1999 the respondent experienced financial difficulties and was thereafter forced to seek help from its creditors through a scheme of arrangement. Its financial position did not improve substantially, however, and this led the creditors to appoint Mr Duar Tuan Kiat (“the Receiver”) as receiver and manager of the respondent on 30 November 2006. From then onwards, the respondent acted under the direction of the Receiver and the powers of the directors were displaced.
In the meantime, the appellant, Marty Ltd, had entered the scene in August 2006 as a company incorporated in the BVI by the Oung brothers. The Oung brothers are and were at all material times the only shareholders of the appellant.
Events occurring after the appellant’s incorporationIn March 2007, Hualon Chemical subscribed for further shares in the Vietnam Subsidiary and E-Hsin transferred its shares in the Vietnam Subsidiary to the appellant (“the 2007 transfers”). The allegation is that the 2007 transfers were procured by the Oung brothers.
In February 2008, the Vietnam Subsidiary was re-registered for the purpose of obtaining an investment certificate from the relevant authorities. As part of the re-registration process, the Vietnam Subsidiary’s company charter was revised and updated (“the Revised Charter”). The Revised Charter contains a number of articles which are relevant to the issues between the parties but we need only mention two:
In August 2008, Hualon Chemical transferred all of its shares in the Vietnam Subsidiary to the appellant and another BVI company, Cubic Holdings Limited, a company whose ownership remains unknown (“the 2008 transfers”). The respondent’s position is that the 2008 transfers were also procured by the Oung brothers. After the 2008 transfers, the shareholders of the Vietnam Subsidiary were the appellant (now holding 99.7% of the shares), Cubic Holdings Limited (holding 0.11% thereof) and the respondent (whose shareholding was reduced to only 0.19%). The 1999, 2007 and 2008 share transfers (collectively the “Share Transfers”) and the parties’ capital contributions as recorded in Art 7 of the Revised Charter formed the basis of the dispute between the parties. The respondent’s position is that the Share Transfers were invalid and that its ownership of the Vietnam Subsidiary has been unlawfully diluted to almost nothing.
Events leading to the disputes and the litigation Due diligence conducted on the Vietnam SubsidiaryIn February 2009, the Receiver commissioned Indochine Counsel, a law firm in Vietnam, to undertake a “limited due diligence/check” on the Vietnam Subsidiary. Indochine Counsel’s proposed scope of services, which was approved and accepted by the Receiver, included obtaining the corporate records of the Vietnam Subsidiary.
On 1 July 2009, Indochine Counsel sent its report dated 19 June 2009 (the “Due Diligence Report”) to the Receiver. In the section titled “Our Advice”, Indochine Counsel set out its advice on the consequences and legal redress under the laws of Vietnam in respect of the transfer of capital from the respondent to the appellant. It took the view that the respondent’s representative (
From 2009 to 2014, the Receiver investigated the matters that were raised in the Due Diligence Report, including by taking steps to locate the individuals involved and to scrutinise the Share Transfers. On 22 July 2014, when he considered enough material had been gathered, the Receiver commenced proceedings in the BVI courts on behalf of the respondent against the appellant and the Oung brothers (“the BVI Action”). In the statement of claim it filed in the BVI Action on the same day, the respondent alleged that it had been wrongfully deprived of its shareholding in the Vietnam Subsidiary. According to the statement of claim, the Oung brothers had breached their statutory and fiduciary duties and the appellant had dishonestly assisted the Oung brothers and knowingly received shares in the Vietnam Subsidiary to which it was not entitled and was thereby unjustly enriched. The respondent then applied for and obtained leave to serve the cause papers on the Oung brothers out of jurisdiction and also obtained an injunction restraining the appellant from disposing of its interest in the Vietnam Subsidiary (“the Interim Injunction”).
The appellant received the cause papers on 13 October 2014 and filed its Acknowledgment of Service on 4 November 2014. On the relevant form, the appellant checked the “YES” box in response to the question as to whether it intended to defend the claim. However, no defence was ever filed.
Subsequently, the appellant and the Oung brothers filed separate challenges against the BVI court’s jurisdiction on the ground of
To continue reading
Request your trial-
Dayang (Hk) Marine Shipping Co., Ltd v Asia Master Logistics Ltd
...forum, they would be in (possibly repudiatory) breach of the arbitration agreement. In Marty Ltd v Hualon Corp (Malaysia) Sdn Bhd [2018] 2 SLR 1207, Judith Prakash JA at pp.1222-1223; §54 “it is strongly arguable that the commencement of court proceedings is itself a prima facie repudiation......
-
Founder Group (Hong Kong) Ltd v Singapore JHC Company Pte Ltd
...[2010] 3 SLR 542 (folld) Fiona Trust & Holding Corp v Privalov [2007] 4 All ER 951 (folld) Marty Ltd v Hualon Corp (Malaysia) Sdn Bhd [2018] 2 SLR 1207 (folld) Metalform Asia Pte Ltd v Holland Leedon Pte Ltd [2007] 2 SLR(R) 268; [2007] 2 SLR 268 (folld) National Mutual Life Association of A......
-
Sulzer Pumps Spain, SA v Hyflux Membrane Manufacturing (S) Pte Ltd
...The first respondent relied on the following passage from Marty Ltd v Hualon Corp (Malaysia) Sdn Bhd (receiver and manager appointed) [2018] 2 SLR 1207 (“Marty”) (at [54]):123 We pause to observe that although Mr Jeyaretnam SC was content to accept that the commencement of the BVI Action al......
-
Bna v Bnb and Another
...SLR 413 (refd) Dyna-Jet Pte Ltd v Wilson Taylor Asia Pacific Pte Ltd [2017] 3 SLR 267 (refd) Marty Ltd v Hualon Corp (Malaysia) Sdn Bhd [2018] 2 SLR 1207 Naviera Amazonica Peruana SA v Compania Internacional de Seguros del Peru [1988] 1 Lloyd’s Rep 116 (refd) PT Garuda Indonesia v Birgen Ai......
-
Conflict of Laws
...6DM (S) Pte Ltd v AE Brands Korea Ltd [2021] SGHC 257 at [89]. 125 See para 12.86 above. 126 Marty Ltd v Hualon Corp (Malaysia) Sdn Bhd [2018] 2 SLR 1207 at [51] – [52], per Judith Prakash JA. 127 The Jian He [1999] 3 SLR(R) 432 at [47], per Chao Hick Tin JA. 128 Vinmar Overseas (Singapore)......
-
Arbitration
...Rev Ed. 34 Available at https://www.ibanet.org/publications/publications_iba_guides_and_free_materials.aspx (accessed April 2019). 35 [2018] 2 SLR 1207. 36 The Mercanaut [1980] 2 Lloyd's Rep 183 (cited in Chitty on Contracts vol 2 (Hugh Beale gen ed) (Sweet & Maxwell, 32nd Ed, 2015) at para......