Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd
| Jurisdiction | Singapore |
| Judge | Aedit Abdullah JC |
| Judgment Date | 25 May 2015 |
| Neutral Citation | [2015] SGHC 141 |
| Year | 2015 |
| Date | 25 May 2015 |
| Published date | 05 June 2015 |
| Hearing Date | 09 January 2015 |
| Plaintiff Counsel | Chia Chee Hyong Leonard and Tan Hin Wa Jason (Asia Ascent Law Corporation) |
| Citation | [2015] SGHC 141 |
| Defendant Counsel | Lam Kuet Keng Steven John (Templars Law LLC) |
| Court | High Court (Singapore) |
| Docket Number | Originating Summons No 915 of 2014 |
The plaintiff in this case seeks to resist the enforcement of an adjudication determination dated 1 October 2014 made pursuant to the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the SOPA”). What is unusual, however, is that the plaintiff’s application is not made pursuant to O 95 r 3 of the Rules of Court (Cap 322, R 5, 2014 Rev Ed) which requires the plaintiff to provide security for the unpaid portion of the adjudicated amount that he is required to pay in consequence of the adjudication determination at the time of the filing of the application.
Instead, the plaintiff, without providing security, seeks a declaration that the adjudication determination is null and void and, in the alternative, a declaration that the adjudicator lacked jurisdiction to adjudicate the matter under the SOPA. He alleges,
Lastly, in the event that the court refuses to grant the declarations sought, the plaintiff requests for an order to stay the enforcement of the adjudication determination.
Facts BackgroundThe plaintiff and the defendant were engaged in an employer-contractor relationship under a building and construction contract entered into on 10 December 2008 which incorporated Singapore Institute of Architects’ Articles and Conditions of Building Contract (Lump Sum Contract) (7th Ed, April 2005) (“the SIA Conditions 2005”) .1 The agreed fee was $1,906,891.31 and 5 December 2009 was the stipulated date for completion.2
The defendant was unable to complete its works by the completion date and the architect for the building project issued a delay certificate on 10 December 2009. The architect thereafter only issued the completion certificate on 3 March 2011, certifying that the defendant had completed its works.3 Prior to this, the defendant had issued 15 progress payment claims and corresponding interim architect’s certificates were issued pursuant to the mechanism provided for under cl 31 of the SIA Conditions 2005. The fifteenth progress payment claim and corresponding interim certificate were issued on 23 June 2010 and 6 July 2010 respectively.4 The plaintiff paid the amounts certified in all of the 15 interim certificates issued.
Payment claims leading up to the adjudicationOn 22 February 2012, the architect reminded the defendant to submit its “final claim”5 pursuant to cl 31(11) of the SIA Conditions 2005 which provides as follows:
Final Claim Documents
The defendant thereafter served on the architect a payment claim which it referred to as “Progress Claim No.16A (FINAL ACCOUNT)” on 27 February 2012.6 I shall henceforth refer to this payment claim as “Payment Claim 16A”. Payment Claim 16A did not specify which period of time for works done by the defendant it related to. Instead, it purported to represent the “FINAL SUMMARY (FINAL ACCOUNT)”7 for works done by the defendant. The architect and quantity surveyor, assuming that Payment Claim 16A was intended to be the defendant’s final claim under cl 31(11) of the SIA Conditions 2005, did not take any action because the defendant failed to produce the supporting documents needed for the preparation of the Final Account as required under that very clause.
After some intermittent communications between the parties, and upon the request of the plaintiff for the defendant to issue its final claim pursuant to cl 31(11) of the SIA Conditions 2005, the defendant served another payment claim on 6 January 2014. The respective letter attaching the payment claim states as follows:8
RE: 4 TAI YUAN HEIGHTS – PROGRESS CLAIM NO. 16B (FINAL ACCOUNT) We refer to the above and are pleased to submit herewith our Progress Claim No.16B (FINAL ACCOUNT) for your perusal and consideration.
The quantity surveyor then sought to clarify with the defendant the nature of Payment Claim 16B. In an email from the quantity surveyor, Mr Oliver Ho (“Mr Ho”) to an employee of the defendant, Ms Angie Ang (“Ms Ang”), dated 27 January 2014, Mr Ho asked:10
Hi Angie,
Please confirm whether your Claim No 16B is actually your
Final Account Document submissionpursuant to [cl] 31(11)(a) of the SIA Conditons [sic ] of Contract.[emphasis added]
Dear Oliver
We would like to confirm that our Claim No.16B dated 6 January 2014 is our
Final Account .[emphasis added]
It bears noting that the SIA Conditions 2005 does not contain a cl 31(11)(a). Clause 31(11) of the SIA Conditions 2005 does not contain any sub-clauses (see above at [6]). Rather, cl 31(11)(a) is only found in later editions of the standard form contract, such as the most recent Singapore Institute of Architects’ Articles and Conditions of Building Contract (Lump Sum Contract) (9th Ed, Reprint August 2011) (“the SIA Conditions 2011”). Clause 31(11) of the SIA Conditions 2011 in fact provides for a final claim procedure different from that found in cl 31(11) of the SIA Conditions 2005:
Final Account Documents
(whichever is the later) provide to the Contractor the Statement of Final Account which shall show the Architect’s final measurement and valuation of all Works carried out together with any permitted deductions (including liquidated damages) under the terms of the Contract whether or not such deductions have been made by the Employer unless in respect of permitted deductions not yet made by the Employer, the Employer has informed the Architect of his decision to forgo or postpone the same.
…
It thus appears to be the case that both the quantity surveyor and the defendant had, at least as of 27 January 2014, proceeded on the incorrect basis that it was the SIA Conditions 2011 (or any other editions of the standard form contract subsequent to the SIA Conditions 2005) that governed the final claim procedure instead of the SIA Conditions 2005 that was incorporated into the building contract between the parties. This is a significant point which I will return to later on in this judgment.
Upon confirmation by the defendant that Payment Claim 16B was intended to be a “Final Account”, the parties, including the quantity surveyor, began to prepare the Final Account. However, the documentation provided together with Payment Claim 16B was deemed deficient by quantity surveyor and more documents were requested. The documentation required for the preparation of the Final Account pursuant to cl 31(11) of the SIA Conditions 2005 was only fully consolidated on 26 June 2014. The architect then issued the maintenance certificate on 30 June 2014 and began to prepare the final certificate pursuant to cl 31(12)(a) of the SIA Conditions 2005 which provides as follows:
Final Certificate
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete access to the largest collection of common law case law on one platform
-
Generate AI case summaries that instantly highlight key legal issues
-
Advanced search capabilities with precise filtering and sorting options
-
Comprehensive legal content with documents across 100+ jurisdictions
-
Trusted by 2 million professionals including top global firms
-
Access AI-Powered Research with Vincent AI: Natural language queries with verified citations
Start Your 7-day Trial
-
Hyundai Engineering & Construction Company Ltd International Elements Pte Ltd
...had to be construed in the context of the Act. The defendant pointed me to Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd [2015] 4 SLR 615 (“Lau Fook Hong”) at [26], in which the court discussed the purpose of s 27(5): With regard to the requirement for the provision of securi......
-
UES Holdings Pte Ltd v Grouteam Pte Ltd
...should be invalid (ie, a breach of a mandatory condition of the Act). In Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd [2015] SGHC 141, Aedit Abdullah JC proffered his views (at [50]–[51]), albeit obiter, that s 10(2)(a) is framed in mandatory terms and must be observed stric......
-
CEQ v CER
...amount that was paid into court pursuant to s 27(5) of the Act: Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd [2015] 4 SLR 615 at [26]. Notwithstanding this, the court clearly retains the power to stay the enforcement of such an adjudication determination. This power flows fr......
-
Kingsford Construction Pte Ltd v A Deli Construction Pte Ltd
...materially different from the two Payment Claims No 14.22 Kingsford cited Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd [2015] 4 SLR 615 (“Lau Fook Hoong”) to support its argument that the two Payment Claims No 15 were invalid as the two Payment Claims No 14 were labelled as ......
-
Building and Construction Law
...submitted a final claim made pursuant to the terms of a contract. 7.35 In Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd[2015] 4 SLR 615 (‘Lau Fook Hoong Adam’), the subject construction contract incorporated the SIA Conditions 2005. After the issue of the completion certifica......
-
Building and Construction Law
...at [12]. 45 Tactic Engineering Pte Ltd v Sato Kogyo (S) Pte Ltd [2017] SGHC 103 at [14]. 46 Cap 30B, 2006 Rev Ed. 47 [2017] SGHC 174. 48 [2015] 4 SLR 615. 49 Articles and Conditions of Building Contract: Lump Sum Contract (Singapore Institute of Architects, 7th Ed, 2005). 50 Kingsford Const......