L W Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd
Jurisdiction | Singapore |
Judge | Belinda Ang Saw Ean J |
Judgment Date | 29 November 2013 |
Neutral Citation | [2013] SGHC 264 |
Court | High Court (Singapore) |
Docket Number | Originating Summons No 29 of 2013 |
Published date | 11 December 2013 |
Year | 2013 |
Hearing Date | 26 July 2013,16 April 2013 |
Plaintiff Counsel | Tan Liam Beng, Soh Chun York and Eng Cia Ai (Drew & Napier LLC) |
Defendant Counsel | Chia Swee Chye (Samuel Seow Law Corporation) |
Subject Matter | Arbitration,Award |
Citation | [2013] SGHC 264 |
This is the latest instalment in a long-running dispute between a main contractor and its sub-contractor in relation to the construction of an industrial building at 31 Toh Guan Road East (“the Project”). The present application
OS 29/2013 was filed after the Court of Appeal affirmed the setting aside of an additional award for pre-award interest (“the Additional Award”) issued by a sole arbitrator (“the Tribunal”) pursuant to s 43(4) of the Arbitration Act (Cap 10, 2002 Rev Ed) (“the Act”) on the ground that it had been made in breach of the rules of natural justice, the Tribunal having failed to give the unsuccessful party an opportunity to reply or make submissions on the issue. Full reasons for the setting aside of the Additional Award are reported in the decision of the Court of Appeal in
In bringing OS 29/2013 for,
LWI’s present application is brought under s 45 of the Act. Subsequently, two other provisions, namely s 36 and s 21(9) of the Act, were introduced. The defendant, Lim Chin San Contractors Pte Ltd (“LCSC”), opposes this application in its entirety. LCSC’s position is that LWI’s application is fundamentally misconceived as none of the statutory provisions apply to this case.
Background to OS 29/2013 Events leading up to the setting aside of the Additional Award.LWI, the main contractor for the Project, appointed LCSC as its sub-contractor under a sub-contract which contained an arbitration clause. Subsequently, various disputes arising out of the sub-contract were referred to arbitration. On 29 June 2010, the Tribunal rendered an award (“the Final Award”) in which LWI was awarded the sum of $341,391.10 “with simple interest at the rate of 5.33% p.a. from the date of this Award”. On 15 July 2010, a supplementary award was issued to correct certain typographical errors in the Final Award.
Being dissatisfied with the Tribunal’s decision, LWI filed an appeal on various questions of law by way of Originating Summons No 759 of 2010 (“OS 759/2010”). LCSC filed a cross-appeal by way of Originating Summons No 769 of 2010. On 5 July 2011, the High Court dismissed LCSC’s appeal and substantially allowed LWI’s appeal. On 21 September 2011, following the Orders of Court handed down by the High Court, the Tribunal rendered another supplementary award (“the Supplementary Award”), in which LWI was awarded the sum of $603,608.90 with “simple interest at the rate of 5.33% p.a. on the sum of S$603,608.90 from the date of this Supplementary Award” (
After reviewing the Supplementary Award, LWI was of the view that the Tribunal had omitted to award pre-award interest on the sum, and requested the Tribunal to grant an additional award for pre-award interest by way of a written request dated 17 October 2011 (“the First Request”). Three days passed. The other party, LCSC, did not respond to the request. On 20 October 2011, the Tribunal then rendered the Additional Award providing for pre-award interest in favour of LWI.
Subsequently, LCSC successfully applied to the High Court under Originating Summons No 988 of 2011 (“OS 988/2011”) to set aside the Additional Award on the ground that it had been made in breach of the rules of natural justice. The High Court however declined to declare the Additional Award a nullity on the basis that the court did not have an inherent or residual discretion to make a declaration as to the validity of an arbitral award outside the express statutory grounds for setting aside.
LWI appealed the decision to set aside the Additional Award and LCSC cross-appealed against the decision not to declare the Additional Award a nullity. On 18 October 2012, in
Events after the setting aside of the Additional AwardBy reason of the matters aforesaid, we affirm the decision of the Judge setting aside the Additional Award. In the course of the arguments, we invited submissions on whether and if so what consequential orders we should make in this event. Counsel for the parties had different views. Mr Tan for [LWI] suggested that the proper course would be for us to remit the matter to the Arbitrator. Mr Chia Swee Chye Kelvin ("Mr Chia") for [LCSC] did not agree that this would be appropriate in the circumstances. Mr Chia contended that (a) it was doubtful whether the court had a power to remit at all in such circumstances; (b) the only relief sought was for the Additional Award to be set aside and once that was done, it was up to [LWI] to attempt to revive its application, and if they did so, [LCSC] would contend that this was impermissible because it would fall outside the statutory time limits provided in the Act for an application to be made under s 43(4) of the Act; and (c) even if these hurdles could be overcome, [LCSC] might have objections to the matter being returned to the Arbitrator in all the circumstances.
These points were not fully argued before us. Furthermore, the only issue before us was whether the order setting aside the Additional Award should be affirmed. Accordingly, we confine ourselves to this and make no special consequential orders. [emphasis added]
Taking the position that the setting aside of the Additional Award returned the arbitral proceedings to the state that existed up to the moment immediately preceding the making of the Additional Award and by way of a letter dated 31 October 2012 (“the Revival Request”), LWI wrote to the Tribunal reiterating its request made on 17 October 2011 for an additional award of pre-award interest to be issued. The parties exchanged several rounds of submissions in the form of letters.
LCSC marshalled the points foreshadowed in
On 14 December 2012, the Tribunal wrote to the parties stating that: (a) the setting aside of the Additional Award did not revive his jurisdiction; and (b) in any case, the last day for him to make an additional award was 16 December 2011, 60 days after his receipt of the First Request (
Disagreeing with the Tribunal’s view, LWI brought the present application in OS 29/2013. LWI’s original application proceeded on two bases:
To continue reading
Request your trial-
LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd
...W Infrastructure Pte Ltd Plaintiff and Lim Chin San Contractors Pte Ltd Defendant [2013] SGHC 264 Belinda Ang Saw Ean J Originating Summons No 29 of 2013 High Court Arbitration—Award—Application under s 21 (9) Arbitration Act (Cap 10, 2002 Rev Ed) for court to decide on plea as preliminary ......