International Research Corporation Plc v

JurisdictionSingapore
Judgment Date12 November 2012
Date12 November 2012
Docket NumberOriginating Summons No 636 of 2012
CourtHigh Court (Singapore)
International Research Corp PLC
Plaintiff
and
Lufthansa Systems Asia Pacific Pte Ltd and another
Defendant

Chan Seng Onn J

Originating Summons No 636 of 2012

High Court

Arbitration—Arbitral tribunal—Jurisdiction—Whether arbitration clause in main agreement was binding on third party to supplementary agreement—Effect of condition precedent to commencement of arbitration

The plaintiff entered into two agreements with the two defendants. These two agreements were supplementary agreements to a main agreement which was entered into between the two defendants. The main agreement contained a dispute resolution mechanism which prescribed that any dispute shall first be resolved by specified a mediation procedure, failing which, the dispute shall be resolved by arbitration. After several rounds of meetings to attempt to resolve the dispute had failed, the first defendant commenced arbitration proceedings against the plaintiff and second defendant. The plaintiff challenged the jurisdiction of the arbitral tribunal on the grounds that it was not bound by the arbitration agreement and even if it was, the condition precedent to the commencement of arbitration had not been satisfied as the parties had not attempted the mediation procedure. The arbitral tribunal rejected the plaintiff's challenge by way of a preliminary ruling on jurisdiction. The plaintiff applied to the High Court to set aside the arbitral tribunal's ruling on jurisdiction on the same grounds canvassed before the arbitral tribunal.

Held, dismissing the application:

(1) The strict rule that clear words were required to incorporate an arbitration agreement was not applicable on the present facts. The question was whether by entering into the supplementary agreements, the plaintiff and the two defendants had intended that the terms of the main agreement, in particular the dispute resolution mechanism, were to be binding on all three parties: at [33] to [44] and [48] to [51].

(2) The plaintiff's obligations in the supplementary agreements were linked to the terms of the main agreement. The plaintiff was aware of the context of the main agreement and the reasons for the three parties entering into the supplemental agreements. In these circumstances, it was unlikely that the parties intended for different dispute resolution mechanisms - the applicability of which depends on the identity of the parties - to resolve the same issue in dispute: at [70] to [73].

(3) By using language which stressed that the supplementary agreements were annexed to and made a part of the main agreement, the parties had objectively intended for the dispute resolution mechanism in the main agreement to be binding on all three parties to the supplementary agreements. This was the only commercially sensible and rational conclusion and this conclusion was not opposed by language in either the dispute resolution mechanism or the supplementary agreements: at [78].

(4) The mediation procedure was not a bare agreement to negotiate. It was part of a broader dispute resolution mechanism. The procedure was certain as it was expressed to be mandatory and had prescribed the various steps and stages of the procedure. The court was in a position to discern if the mediation procedure was complied with: at [90] to [97].

(5) The mediation procedure was a condition precedent to the commencement of arbitration. A duty to arbitrate did not arise until the condition precedent was satisfied: at [103].

(6) The first defendant had complied in substance with the mediation procedure as there had been numerous high-level meetings between the parties to resolve the very dispute which was the subject of the arbitration proceedings: at [110].

[Observation: While a party who was dissatisfied with the arbitral tribunal's preliminary ruling on jurisdiction was permitted to apply to the Singapore court to have the Singapore court decide the matter, the court might be precluded from setting aside the ruling on jurisdiction as such a ruling was not an award: at [111] to [113].]

Africa Express Line Ltd v Socofi SA [2010] 2 Lloyd's Rep 181 (refd)

AIG Europe SA v QBE International Insurance Ltd [2001] 2 Lloyd's Rep 268 (refd)

Astrata (Singapore) Pte Ltd v Portcullis Escrow Pte Ltd [2011] 3 SLR 386 (refd)

Aughton Ltd v MF Kent Services Ltd (1991) 57 BLR 1 (refd)

Bank of Credit and Commerce International SA v Ali [2002] 1 AC 251 (refd)

Cable & Wireless Plc v IBM United Kingdom Ltd [2002] CLC 1319 (refd)

Chartbrook Ltd v Persimmon Homes Ltd [2009] 1 AC 1011 (refd)

Concordia Agritrading Pte Ltd v Cornelder Hoogewerff (Singapore) Pte Ltd [1999] 3 SLR (R) 618; [2001] 1 SLR 222 (refd)

Coop International Pte Ltd v Ebel SA [1998] 1 SLR (R) 615; [1998] 3 SLR 670 (distd)

Econ Piling Pte Ltd v NCC International AB [2007] SGHC 17 (refd)

Emmott v Michael Wilson & Partners (No 2) [2009] Bus LR 723; [2009] EWHC 1 (Comm) (distd)

Faghirzadeh v Rudolf Wolff (SA) (Pty) Ltd [1977] 1 Lloyd's Rep 630 (refd)

Federal Bulker, The [1989] 1 Lloyd's Rep 103 (refd)

Fiona Trust & Holding Corp v Privalov [2007] Bus LR 1719; [2008] 1 Lloyd's Rep 254 (refd)

Fletamentos Maritimos SA v Effjohn International BV [1996] 2 Lloyd's Rep 304 (refd)

Grossman v Hooper [2001] 2 EGLR 82 (refd)

Habas Sinai Ve Tibbi Gazlar Isthisal Endustri AS v Sometal SAL [2010] Bus LR 880; [2010] EWHC 29 (Comm) (refd)

HIM Portland LLC v Devito Builders Inc 317 F 3 d 41 (1 st Cir, 2003) (folld)

HSBC Institutional Trust Services (Singapore) Ltd v Toshin Development Singapore Pte Ltd [2012] 4 SLR 738 (folld)

Insigma Technology Co Ltd v Alstom Technology Ltd [2009] 1 SLR (R) 23; [2009] 1 SLR 23, HC (distd)

Insigma Technology Co Ltd v Alstom Technology Ltd [2009] 3 SLR (R) 936; [2009] 3 SLR 936, CA (refd)

Investors Compensation Scheme Ltd v West Bromwich Building Society [1998] 1 WLR 896 (refd)

L&M Concrete Specialists Pte Ltd v United Eng Contractors Pte Ltd [2000] 2 SLR (R) 852; [2000] 4 SLR 441 (refd)

Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] AC 749 (refd)

Master Marine AS v Labroy Offshore Ltd [2012] 3 SLR 125 (refd)

PT Asuransi Jasa Indonesia (Persero) v Dexia Bank SA [2007] 1 SLR (R) 597; [2007] 1 SLR 597 (refd)

Sea Trade Maritime Corp v Hellenic Mutual War Risks Association (Bermuda) Ltd (The Athena) (No 2) [2007] 1 Lloyd's Rep 280 (refd)

Sigma Finance Corp, Re [2008] EWCA Civ 1303 (refd)

Sigma Finance Corp, Re [2009] UKSC 2 (refd)

Smith v Chadwick (1882) 20 Ch D 27 (refd)

Smith v Martin [1925] 1 KB 745 (refd)

Star-Trans Far East Pte Ltd v Norske-Tech Ltd [1996] 2 SLR (R) 196; [1996] 2 SLR 409 (distd)

Svenska Petroleum Exploration AB v Government of the Republic of Lithuania (No 2) [2007] QB 886 (folld)

TWThomas & Co Ltd v Portsea Steamship Co Ltd [1912] AC 1 (refd)

Thornton v Shoe Lane Parking Ltd [1971] 2 QB 163 (refd)

Tjong Very Sumito v Antig Investments Pte Ltd [2009] 4 SLR (R) 732; [2009] 4 SLR 732 (distd)

Tootal Clothing Ltd v Guinea Properties Management Ltd [1992] 2 EGLR 80 (refd)

Walford v Miles [1992] 2 AC 128 (distd)

Yamashita Tetsuo v See Hup Seng Ltd [2009] 2 SLR (R) 265; [2009] 2 SLR 265 (refd)

Zurich Insurance (Singapore) Pte Ltd v B-Gold Interior Design & Construction Pte Ltd [2008] 3 SLR (R) 1029; [2008] 3 SLR 1029 (refd)

International Arbitration Act (Cap 143 A, 2002 Rev Ed) ss 10, 24

Subramanian Pillai and Jasmin Yek (Colin Ng & Partners LLP) for the plaintiff

Dhillon Dinesh Singh, Tan Xeauwei, Joel Lim and Teh Shi Ying (Allen & Gledhill LLP) for the first defendant.

Judgment reserved.

Chan Seng Onn J

Introduction

1 This case concerns the challenge of an arbitral tribunal's (‘the Tribunal’) ruling on jurisdiction pursuant to s 10 of the International Arbitration Act (Cap 143 A, 2002 Rev Ed) (‘the IAA’). The gist of the challenge is whether an arbitration clause contained in one contract between two parties binds a third party who subsequently enters into a supplemental agreement with the original two parties.

Background

Parties

2 The plaintiff, International Research Corporation Public Company Ltd (‘IRCP’), is a company engaged primarily in the business of providing information and communication technology products and services. The first defendant, Lufthansa Systems Asia Pacific Pte Ltd (‘Lufthansa’), is in the business of providing information technology services to companies in the aviation industry. The second defendant, Datamat Public Company Ltd (‘Datamat’), provides information and computer technology services, including the distribution of hardware and software maintenance services.

3 Lufthansa is the claimant and IRCP and Datamat are the respondents in SIAC Arb No 061 of 2010 (‘the arbitration proceedings’) which was instituted by Lufthansa on 13 May 2010.

Facts

The Cooperation Agreement

4 The dispute in the arbitration proceedings pertains to payments due to Lufthansa under the Cooperation Agreement for Application and Services Implementation SAP R/3 IS A&D Contract No LSY ASPAC 1 ZW-B (‘the Cooperation Agreement’) entered into between Lufthansa and Datamat on or about 11 March 2005. Under the Cooperation Agreement, Lufthansa agreed to supply, deliver and commission a new maintenance, repair and overhaul system (‘MRO System’). The MRO System was a component of the electronic data protection system (‘the EDP System’) which Datamat had agreed to provide to Thai Airways International Public Company Ltd (‘Thai Airways’) under an agreement between Datamat and Thai Airways entered into earlier on 12 January 2005 (‘the EDP System Agreement’).

IRCP's initial involvement with Datamat

5 On or about 14 March 2005, Datamat entered into a sale and purchase agreement (‘the S&P Agreement’) with IRCP under which IRCP had three main obligations. First, IRCP would provide a bankers' guarantee in the name of Datamat in order for Datamat to comply with its obligations under the...

To continue reading

Request your trial
2 cases
  • International Research Corporation Plc v Lufthansa Systems Asia Pacific Pte Ltd
    • Singapore
    • Court of Appeal (Singapore)
    • 18 October 2013
    ...The Judge's written judgment (‘the Judgment’) is reported in International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd[2013] 1 SLR 973. On 16 August 2013, having considered the written submissions filed by the parties as well as the oral submissions of counsel, we allowed the......
  • CZQ and another v CZS
    • Singapore
    • International Commercial Court (Singapore)
    • 27 October 2023
    ...a condition precedent to legal proceedings” (Ruling at [461]); International Research Corp PLC v Lufthansa Systems Asia Pacific Pte Ltd [2013] 1 SLR 973 (“Lufthansa (HC)”) at [100] where the High Court endorsed the parties’ common premise that Clause 37.2 was a condition precedent to the co......
6 books & journal articles
  • MEDIATION CLAUSES
    • Singapore
    • Singapore Academy of Law Journal No. 2019, December 2019
    • 1 December 2019
    ...Pte Ltd [2012] 4 SLR 738 at [40], per V K Rajah JA, followed in International Research Corp plc v Lufthansa Systems Asia Pacific Pte Ltd [2013] 1 SLR 973 (the High Court decided that a multi-tiered dispute resolution clause was enforceable). 51 Maud Piers, “Europe's Role in Alternative Disp......
  • Contract Law
    • Singapore
    • Singapore Academy of Law Annual Review No. 2012, December 2012
    • 1 December 2012
    ...approach might be rectification. Indeed, the High Court in International Research Corp plc v Lufthansa Systems Asia Pacific Pte Ltd[2013] 1 SLR 973 very helpfully noted (at [53]) that the language in the agreement is an important starting point but such plain meaning is insufficient as the ......
  • Arbitration
    • Singapore
    • Singapore Academy of Law Annual Review No. 2012, December 2012
    • 1 December 2012
    ...to the different agreements confronted Chan Seng Onn J in International Research Corp plc v Lufthansa Systems Asia Pacific Pte Ltd[2013] 1 SLR 973 (‘International Research Corp plc’), where Lufthansa Systems Asia Pacific Pte Ltd (‘Lufthansa’) and Datamat Public Company Ltd (‘Datamat’) were ......
  • Arbitration
    • Singapore
    • Singapore Academy of Law Annual Review No. 2013, December 2013
    • 1 December 2013
    ...Court affirmed the tribunal's ruling upholding jurisdiction (see International Research Corp plc v Lufthansa Systems Asia Pacific Pte Ltd[2013] 1 SLR 973) ruling that by using language which stressed that the supplemental agreements were ‘annexed to and made a part of the [Co-operation Agre......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT