GA Engineering Pte Ltd v Sun Moon Construction Pte Ltd
Judge | Vinodh Coomaraswamy J |
Judgment Date | 06 August 2020 |
Neutral Citation | [2020] SGHC 167 |
Citation | [2020] SGHC 167 |
Court | High Court (Singapore) |
Published date | 14 August 2020 |
Docket Number | Suit No 521 of 2017 |
Plaintiff Counsel | Tan Beng Swee and Leonard Lee (CTLC Law Corporation) |
Defendant Counsel | Xhuanelado Owen (Kalco Law LLC) |
Subject Matter | Building and Construction Law,Building and construction contracts,Lump sum contract,Sub-contracts,Incorporation of main contract terms,Damages,Damages for defects |
Hearing Date | 04 July 2019,01 July 2019,02 July 2019,03 July 2019,09 September 2019 |
This action arises out of a lump sum contract which the plaintiff and the defendant entered into in June 2014 (the “Subcontract”).1 Under the Subcontract, the defendant as subcontractor undertook to design, supply and install various furnishings for the plaintiff as main contractor (the “Works”). The Works included a glass curtain wall system, aluminium and glazing works and a feature wall for a freehold industrial development (the “Project”). The Subcontract price was $2.19m. 2
The Temporary Occupation Permit (“TOP”) for the Project was issued in June 2016. The architect issued the Certificate of Completion (“CoC”) in November 2016, but with retrospective effect from July 2016.3 From July 2016 to December 2016, the plaintiff handed over completed units to individual subsidiary proprietors. The Building and Construction Authority of Singapore (“BCA”) issued the Certificate of Statutory Completion (“CSC”) in August 2017.4
The parties’ claims The plaintiff’s case is that the defendant has breached the Subcontract by:5
The defendant rejects the plaintiff’s claim and brings a counterclaim for the following:6
This action has been bifurcated. Accordingly, I am in this trial concerned only with liability. There will be a separate assessment of damages to fix quantum.
The issues on liability which I have to determine on the plaintiff’s claim are:
The issues on liability which I have to determine on the defendant’s counterclaim – insofar as those issues have not otherwise been dealt with in determining the plaintiff’s claim – are:
Having considered the evidence and the parties’ submissions, I have arrived at the following findings on the defendant’s liability on the plaintiff’s claim:
I have also arrived at the following findings on the plaintiff’s liability on the defendant’s counterclaim:
The Glass Defects Issue concerns white spots, specks and bubbles which appeared on the glass panels (collectively, the “Glass Defects”) which the defendant installed as part of the glass curtain wall for the Project.8 It is common ground that the Glass Defects were not present when the glass was installed and began to appear only after TOP was issued in June 2016.9
The parties carried out a series of joint inspections on-site from July 2016 to October 2016. They were unable to resolve the issue. 10
The plaintiff initially employed the term “Delamination Defects” to describe the Glass Defects in its statement of claim. However, the plaintiff confirmed at a pre-trial conference that “delamination” was used as a shorthand term to refer to the Glass Defects and not in its technical sense to mean a defect such as the Polyvinyl Butyral (“PVB”) layer between the sheets of laminated glass becoming detached.11 I shall proceed to determine the Glass Defects Issue on this basis.
The parties’ positionsThe plaintiff argues that the appearance of the Glass Defects constitutes breaches of various terms of the Subcontract. The plaintiff accepts that it is the white spots and specks which form the bulk of the Glass Defects.12
The plaintiff’s case is that the Glass Defects are a failure to comply with cll 2.2.1(a) and 2.2.8(b) of the Architectural Specifications (“AS”) in the main contract as well as with cll 3.3.7(b) and 3.3.7(c) of the National Productivity and Quality Specifications (“NPQS”) in the main contract (collectively, “Glass Specifications”).13 These Glass Specifications are incorporated into the Subcontract by cll 8.1 and/or 2.2 of the Subcontract.14 The Glass Defects are also a failure to meet the specification contained in Appendix A of the Subcontract (“Appendix A Specification”).
The defendant submits that it has not failed to meet any of the Glass Specifications and the Appendix A Specification. First, the Glass Specifications and Appendix A of the Subcontract are of no contractual force between the plaintiff and the defendant because they were never validly incorporated into the Subcontract. Second, even if the Glass Specifications have been incorporated into the Subcontract by express reference: (a) the Glass Specifications are concerned only with the surfaces of the glass panels rather than the coating applied to them; and (b) the white spots have not caused any obstruction of vision and there is no suggestion that the emissivity function of the glass coatings is impaired.15 Third, the plaintiff refused to allow the defendant an opportunity to rectify and replace the glass panels.16
Is the plaintiff entitled to recover substantial damages?I begin by considering a preliminary objection raised by the defendant. The defendant argues that the plaintiff is not entitled to claim substantial damages against the defendant because the Glass Defects caused no actual loss to the plaintiff. With the exception of a few replacement works that the plaintiff allegedly carried out in units #03-07, #05-05, #05-06 and #06-03 of the Project,17 the plaintiff has suffered no loss as a result of the Glass Defects. Further, neither the owner nor the individual subsidiary proprietors of any of the units in the Project have commenced any legal proceedings against the plaintiff or have sought to recover any damages from the plaintiff for the Glass Defects.18 The plaintiff thus has not suffered any loss. It should therefore not be entitled to recover damages from the defendant for the Glass Defects.
The general rule is, of course, that a plaintiff is entitled to recover damages only for loss which a breach of contract causes the plaintiff itself to suffer. The plaintiff, however, relies on the exceptions to that rule recognised by the Singapore Court of Appeal in
In
To continue reading
Request your trial-
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd and another appeal
...the disputes between the parties in any other dispute resolution proceedings. In GA Engineering Pte Ltd v Sun Moon Construction Pte Ltd [2020] SGHC 167 (“GA Engineering”) at [250], Vinodh Coomaraswamy J accepted that the operation of s 30(4) of the SOPA allows a party to an adjudication to ......