Eurogreen Building Products Private Limited v Savourer Pte Ltd
Jurisdiction | Singapore |
Judge | Lewis Tan |
Judgment Date | 01 September 2022 |
Neutral Citation | [2022] SGMC 53 |
Court | Magistrates' Court (Singapore) |
Docket Number | Magistrate Court Originating Claim No 49 of 2022 (Summons No 2889 of 2022) |
Published date | 06 September 2022 |
Year | 2022 |
Hearing Date | 26 August 2022 |
Plaintiff Counsel | Chuah Hui Fen, Christine (Tan Oei & Oei LLC) |
Defendant Counsel | A Rajandran (A Rajandran) |
Subject Matter | Civil Procedure,Pleadings,Striking out,Res judicata |
Citation | [2022] SGMC 53 |
The Claimant sued the Defendant in the Small Claims Tribunal (“SCT”), seeking payment for materials that it had supplied pursuant to a construction contract. The Defendant resisted the claim by relying on a settlement agreement between the parties which allegedly set-off the claimed sum. The tribunal magistrate found that a large portion of the claim and the defence of set-off fell outside his jurisdiction, and so only a small aspect of the claim was disposed of on the merits.
The Claimant then brought the present action, claiming the portion of the invoiced amount which was deemed to fall outside the SCT’s jurisdiction, and the Defendant sought again to set off this amount by relying on the settlement agreement. The Claimant considered this set-off defence to be, amongst others, a re-litigation of matters, and sought to strike off much of the Defence and Counterclaim (“DCC”). After hearing parties, I dismissed the Claimant’s striking out application.
Given that the application was brought under the new Rules of Court 2021 (“ROC 2021”), and with the lack of reported decisions in this regard, I now provide the fuller reasons for my decision.
FactsThe Defendant, Savourer Pte Ltd, was a sub-contractor involved in the refurbishment of the link bridges at Changi Airport Terminal 2. As part of the works, the Defendant engaged the Claimant for the supply of wall and roof panels. In addition, the Defendant sub-contracted the works pertaining to the removal and reinstallation of these roof and wall panels to another contractor, Island Construction Pte Ltd (“Island Construction”).
Amidst the installation of the panels, issues appeared to arise regarding the different colour tones on said panels, and this led to several meetings between the representatives of the Claimant, Defendant, and Island Construction. According to the Defendant, the result of these meetings was that (a) the Claimant would supply replacement panels at its own expense, and (b) Island Construction would carry out the rectification works, which would take an estimated two weeks and cost about $28,000. Upon completion of the rectification works, Island Construction submitted their invoice to the main contractor of the project. The main contractor then invoiced the Defendant for the said works.
It is unclear from the pleadings whether the Defendant has paid Island Construction and/or the main contractor for the rectification works. Nonetheless, any such payment would not have directly affected the Claimant because, as the Defendant pleads, there was an alleged settlement agreement between the Claimant and the Defendant whereby the Claimant would only have to pay the Defendant $20,000 plus Goods and Services Tax (“GST”) for the rectification works carried out by Island Construction (hereinafter, the “Settlement Agreement”). Pursuant to this Settlement Agreement, the Claimant made partial payment of $5,000 plus GST to the Defendant, leaving a sum of $15,000 plus GST owing to the Defendant.
The Claimant strenuously refutes the existence of said Settlement Agreement, and it instructed solicitors to issue a letter of demand claiming $22,682.61 from the Defendant for the supplied materials. Being of the view that $15,000 plus GST ($16,050) remained outstanding under the Settlement Agreement, the Defendant proceeded to tender a cheque for $6,632.61 (
Instead, the Claimant lodged a claim against the Defendant in the SCT, claiming the sum of $16,050.1 The Defendant resisted the claim, arguing that the Claimant had acknowledged its mistake in the supply of certain materials which had already been installed by Island Construction. After some negotiations, the Claimant agreed to compensate $20,000 plus GST, but only $5,350 (
Dealing first with the Claimant’s claim for $16,050, the learned Tribunal Magistrate (“TM”) allowed the claim for $4,791.46. As regards the remaining $11,258.54, the TM held that this sum stemmed from a contract which value exceeded the SCT’s jurisdiction of $20,000, and so that portion of the Claimant’s claim fell outside his jurisdiction. Turning to the Defendant’s defence of set-off, the TM held that this also fell outside of his jurisdiction as the set-off “d[id] not apply to the portion of the claim [
Following the TM’s decision, the Claimant brought the present action, claiming for the remaining $11,258.54 which fell outside the TM’s jurisdiction. The Defendant resisted this claim for much the same reasons provided at [8] above, namely that the claimed sum should be set-off against the $16,050 (
By way of the present summons, the Claimant seeks to strike out portions of the DCC which rely on the Settlement Agreement. According to the Claimant, such references to the Settlement Agreement by the Defendant should be struck out pursuant to O 9 rr 16(1)(
The application was brought under the new ROC 2021 regime, which differs from the Rules of Court 2014 (“ROC 2014”) in substantial ways. For ease of comparison, the rules providing for the striking out of pleadings under both sets of Rules (
| |
| |
The differences notwithstanding, similarities remain – for example, both O 18 r 19(1)(
This approach of referring to decisions that predate the new Rules has also been adopted in other cases where the...
To continue reading
Request your trial