Engineering Construction Pte Ltd v Sanchoon Builders Pte Ltd
Jurisdiction | Singapore |
Court | High Court (Singapore) |
Judge | Quentin Loh J |
Judgment Date | 07 October 2010 |
Neutral Citation | [2010] SGHC 293 |
Citation | [2010] SGHC 293 |
Docket Number | Originating Summons No 321 of 2010 |
Date | 07 October 2010 |
Published date | 05 April 2011 |
Plaintiff Counsel | Philip Jeyaretnam, SC and Benjamin Yam (instructed) (Rodyk & Davidson LLC),Chan Chun Hwee Allan (C H Chan & Co) |
Defendant Counsel | Tan Joo Seng (Chong Chia & Lim LLC) |
Subject Matter | Arbitration |
Hearing Date | 30 June 2010 |
The Plaintiff, subcontractor to the main contractor Defendant, applied for leave under section 49 of the Arbitration Act (Cap 10, 2002 Rev Ed) to appeal to the Court on two questions of law arising from an Arbitration Award dated 1 February 2010.
The FactsThe Defendant tendered for and secured a contract from the West Coast–Ayer Rajah Town Council (“the Town Council”), to carry out certain improvement works at a lump sum of $572,000. The works were broken down into Part A, for $350,000 and Part B, for $222,000. It will be convenient to briefly set out a break down of the works and the contract sums against each item:
| ||
| | |
| | |
| | |
| | |
| | |
| | |
| ||
| | |
| | |
| | |
| | |
The Defendant used its own subcontract form and this subcontract agreement was also dated 30 July 2004. The subcontract period of 6 months from 27 August 2004 to 26 February 2005 mirrored the period stipulated in the main contract between the Defendant and the Town Council.
Disputes arose between the Parties during the course of the subcontract works. In essence, the Plaintiff complained that their interim monthly payments, although certified and paid to the Defendant by the Town Council, were being unjustifiably withheld by the Defendant in breach of their contractual obligation to make payment within 10 days of payment by the Town Council. On the other hand, the Defendant complained that the Plaintiff had insufficient labour at site; was falling unacceptably behind in their progress of the works; lost their project manager and did not replace him and caused these and other complaints to be registered by the consultant, E M Services Pte Ltd (“the Consultant”) against the Defendant.
Alleging a repudiatory breach by non-payment of Payment Certificates Nos. 2 and 3, the Plaintiff terminated its subcontract and abandoned the works on 10 January 2005. The Defendant alleged that the Plaintiff had repudiated the contract by stopping work without justification on 10 January 2005 and accepted their repudiatory breach. In addition, the Defendant alleged that the Plaintiff was in breach of their subcontract by failing to carry out their works diligently and with due expedition, resulting in the Defendant having to take over parts of their works; failed to have a competent project manager; and failed to rectify their defective works. The Defendant also alleged that the Consultant had documented the defaults of the Plaintiff.
The disputes were referred to arbitration in February 2006. The Singapore International Arbitration Centre (“SIAC”) appointed Mr John Chung as the sole arbitrator (“the Arbitrator”), on 6 March 2006. The arbitration hearing was held on 31 August, 1, 3, 4 and 10 September 2009, written closing submissions were made on 8 October 2009 and reply submissions on 5 November 2009 and the Arbitrator published his award on 1 February 2010 (the “Award”).
The Arbitrator ruled in favour of the Defendant, finding and holding as follows:
| | |
| | |
| | |
| | |
| | |
It is from this Award that the Plaintiff seeks leave to appeal on two questions of law. The questions of law set out in the Originating Summons are as follows:
Mr Jeyaretnam SC concentrated on the 2
Mr Jeyaretnam SC relied heavily on the House of Lords decision in
On the above clause, the official referee held that even if it was narrowly construed, it entitled the main contractor to withhold the balance of the amounts due pending determination of their cross claims for unliquidated damages against the sub-contractor for delay and defective work. The Court of Appeal reversed that decision and on appeal the House of Lords allowed the appeal. Besides overruling the case ofThe Contractor also reserves the right to deduct from any payments certified as due to the sub-contractor and/or otherwise to recover the amount of any
bona fide contra accounts and/or other claims which he, the Contractor, may have against the sub-contractor in connection with this or any other contract.
Mr Jeyaretnam SC referred me to the following passage from the judgment of Lord Morris, at 704:
It is upon the interpretation [of the above clause] that the present case, in my view, depends. A ‘certified’ payment is clearly a liquidated sum. To have a process of deduction from such a sum
there must clearly be some other stated sum . There could, for example, be some other liquidated sum. There could be some other sum which could be regarded as a contra account.But there would have to be some sum .There could not be a deduction of something that lacked any kind of specification . But need the sum to be deducted be a liquidated sum or an ascertained sum in the sense of an agreed sum or of a sum assessed by a court? The wording of the provision does not so indicate. There may be adeduction of the amount of anybona fide claim which the contractor may have against the sub-contractor. Such claim may be in connection with the...
To continue reading
Request your trial-
Ng Tze Chew Diana v Aikco Construction Pte Ltd
...or a point of “general public importance”. As explained by Quentin Loh J in Engineering Construction Pte Ltd v Sanchoon Builders Pte Ltd [2011] 1 SLR 681 (“Engineering Construction”) at [49]: It is settled law that the principles set out in [The Nema] prescribe: (a) where the question of la......
-
Strategic Construction Pte Ltd v JH Projects Pte Ltd
...A/S I Likvidation v Ultrapolis 3000 Investments Ltd [2011] 4 SLR 997 (refd) Engineering Construction Pte Ltd v Sanchoon Builders Pte Ltd [2011] 1 SLR 681 (refd) Hua Rong Engineering Pte Ltd v Civil Tech Pte Ltd [2018] 3 SLR 778 (refd) Lim Poh Yeoh v TS Ong Construction Pte Ltd [2017] 4 SLR ......
-
Hayate Investment Co Ltd v ManagementPlus (Singapore) Pte Ltd
...by briefly and broadly examining the contours of the law of set-off. In Engineering Construction Pte Ltd v Sanchoon Builders Pte Ltd [2011] 1 SLR 681, Quentin Loh J defined a set-off (at [12]) as “the taking of two competing money cross-claims, setting off one against the other and producin......