CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd and another
Jurisdiction | Singapore |
Court | High Court (Singapore) |
Judge | Edmund Leow JC |
Judgment Date | 18 December 2014 |
Neutral Citation | [2014] SGHC 266 |
Citation | [2014] SGHC 266 |
Defendant Counsel | Chuah Chee Kian Christopher, Kua Lay Theng, Lydia Binte Yahaya, Candy Agnes Sutedja and Lim Qian Wen Amanda (WongPartnership LLP),Tham Hsu Hsien (Allen & Gledhill LLP) |
Published date | 22 December 2014 |
Date | 18 December 2014 |
Subject Matter | Banking,Performance Bonds |
Plaintiff Counsel | Vikram Nair, Seow Wai Peng Amy and Tan Ruo Yu (Rajah & Tann Singapore LLP) |
Hearing Date | 11 November 2014 |
Docket Number | Originating Summons No 1025 of 2014 |
The first defendant, a property developer, engaged the plaintiff as its main contractor for the development of three blocks of residential flats at Seletar Road, Singapore (“the Project”). Pursuant to the terms of the main contract, the plaintiff provided a performance bond of $8,806,383.80 (
Dissatisfied with the plaintiff’s performance under the contract, the first defendant issued a notice of termination and called on the performance bond. In response, the plaintiff brought the present application praying for an injunction to restrain the first defendant from calling on the performance bond on the ground that the call was unconscionable.
I heard the application on 11 November 2013 and reserved judgment after hearing the parties.
Background to the disputeThe plaintiff began work on the Project on 21 January 2013. Under the main contract, the scheduled completion date was 20 January 2015. The architect named in the main contract was Mr Chan Soo Khian (“the Architect”).
In September 2014, the Architect issued four notices highlighting the plaintiff’s failure to proceed diligently and its non-compliance with certain directions issued by him.
On 23 October 2014, the Architect issued two termination certificates which corresponded to the plaintiff’s failure to comply with two notices. The next day, the first defendant issued its notice of termination to terminate the plaintiff’s employment under the contract on the basis of the termination certificates.
On 3 November 2014, the first defendant engaged a replacement contractor to rectify existing defects and complete the outstanding work on the Project. The contract sum was $59,941,539.26.
The next day, on 4 November 2014, the first defendant called on the performance bond by issuing a letter of demand to the second defendant.
On 5 November 2014, Vinodh Coomaraswamy J heard the plaintiff’s
At the hearing before me, counsel for the plaintiff, Mr Vikram Nair, mentioned in the course of his arguments that arbitral proceedings to determine the dispute between the parties have already been commenced.
The parties’ arguments The plaintiff argues that the call was unconscionable because:
The plaintiff also argues that cl 3.5.8 of the preliminaries (which were incorporated into the main contract) which attempted to prohibit the plaintiff from seeking the present injunction on the ground of unconscionability is unenforceable for being an attempt to oust the court’s jurisdiction.
The first defendant submits there was no unconscionability in its call on the performance bond because:
Two issues arise for my consideration and they are discussed in the following order:
Clause 3.5.8 of the preliminaries1 to the main contract provides:
In keeping with the intent that the performance bond is provided by the [plaintiff] in lieu of a cash deposit, the Contractor agrees that
except in the case of ...
To continue reading
Request your trial-
CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd
...Asplenium's call. Both CKR and Asplenium appealed against the Judge's decision in CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd[2015] 1 SLR 987 (‘the Judgment’). CKR appealed against the Judge's finding that Asplenium did not make the call unconscionably. Asplenium cross-appealed a......
-
E-Tech Building Services Pte Ltd v Foreign Domestic Worker Association for Social Support and Training (FAST)
...Nahyan [2000] 1 SLR(R) 117 at [42] and [57]), or abuse, unfairness or dishonesty (CKR Contract Services Pte Ltd v Asplenium Land Pte Ltd [2015] 1 SLR 987 at [27](a)) on the part of the beneficiary. Genuine dispute as to the existence of a legal entitlement to call. In Ryobi Tactics Pte Ltd ......
-
Injunctive Relief: But Let's Agree Not To Have It?
...Pte Ltd vJoin-Aim Pte Ltd [2012] SGCA 28; [2012] 3 SLR 352 at [23] and [45].4CKR Contract Services Pte Ltd vAsplenium Land Pte Ltd [2014] SGHC 266; [2015] 1 SLR 987(Asplenium (HC)).5ibid at [19] and [20].6ibid at [21].7ibid at [22]-[25].8ibid at [27]-[34].C2016 The Author. The Modern Law R......
-
Attribution and the Illegality Defence
...Pte Ltd vJoin-Aim Pte Ltd [2012] SGCA 28; [2012] 3 SLR 352 at [23] and [45].4CKR Contract Services Pte Ltd vAsplenium Land Pte Ltd [2014] SGHC 266; [2015] 1 SLR 987(Asplenium (HC)).5ibid at [19] and [20].6ibid at [21].7ibid at [22]-[25].8ibid at [27]-[34].C2016 The Author. The Modern Law R......
-
No (,) More Bolam Please: Montgomery v Lanarkshire Health Board
...Pte Ltd vJoin-Aim Pte Ltd [2012] SGCA 28; [2012] 3 SLR 352 at [23] and [45].4CKR Contract Services Pte Ltd vAsplenium Land Pte Ltd [2014] SGHC 266; [2015] 1 SLR 987(Asplenium (HC)).5ibid at [19] and [20].6ibid at [21].7ibid at [22]-[25].8ibid at [27]-[34].C2016 The Author. The Modern Law R......