Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd
Jurisdiction | Singapore |
Court | Court of Three Judges (Singapore) |
Judge | Sundaresh Menon CJ,Tay Yong Kwang JA,Steven Chong JA |
Judgment Date | 02 March 2018 |
Neutral Citation | [2018] SGCA 12 |
Citation | [2018] SGCA 12 |
Plaintiff Counsel | Tan Tian Luh, Ngo Wei Shing and Yap Pei Yin (Chancery Law Corporation) |
Published date | 07 March 2018 |
Subject Matter | Statutes and regulations,Building and Construction Law |
Hearing Date | 19 January 2018 |
Defendant Counsel | Ho Chye Hoon (KEL LLC) |
Date | 02 March 2018 |
Docket Number | Civil Appeal No 153 of 2017 |
The appellant, Civil Tech Pte Ltd (“Civil Tech”), appealed against the decision of the Judge below to dismiss its application to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“the Act”). The central question in this appeal was whether under the Act, a respondent to a payment claim may withhold payment based on a claim or asserted set-off which does not arise from the contract on which the payment claim is based (“the Payment Claim Contract”), but from a separate construction contract regulated by the Act.
The Judge below answered this question in the negative. Civil Tech then brought this appeal against the Judge’s decision. After hearing the appeal, we dismissed it, indicating that we would issue detailed grounds of decision given the importance of the issue at hand. We now deliver the grounds of our decision.
Facts The partiesCivil Tech and the respondent, Hua Rong Engineering Pte Ltd (“Hua Rong”), are Singapore-incorporated companies in the business of building and construction. Civil Tech was engaged as the main sub-contractor for two construction projects by the Land Transport Authority, the T211 project for the construction of the Bright Hill MRT station and the C933 project for the construction of the Jalan Besar MRT station. By two separate contracts (“the T211 Contract” and “the C933 Contract”), Civil Tech engaged Hua Rong as its sub-contractor to supply labour for each of these projects.
The background to the disputeOn 6 December 2016, Hua Rong submitted a payment claim (“the Payment Claim”) in the sum of $601,873.40 to Civil Tech for work under the T211 Contract.
On 21 December 2016, Civil Tech issued a payment certificate, which the parties accepted served as a payment response (“the Payment Response”), certifying a negative sum of $1,571,055.66. In other words, by the Payment Response, Civil Tech claimed that far from being liable to Hua Rong, the latter owed it a substantial sum of money. According to Civil Tech, Hua Rong had made fraudulent payment claims under the
Hua Rong subsequently filed an adjudication application in relation to the Payment Claim. In its adjudication response, Civil Tech again claimed that it had satisfied fraudulent payment claims made by Hua Rong under the C933 Contract, and was entitled to withhold payment of the Payment Claim on this basis.
On 15 February 2017, the adjudicator (“the Adjudicator”) released his determination (“the Adjudication Determination”). The Adjudicator held that the Act did not permit the respondent in an adjudication application to set-off claims arising under another contract against monies due to a claimant under the contract to which the adjudication relates. In the absence of any other asserted defence, the Adjudicator therefore determined that Hua Rong was entitled to the claimed sum of $601,873.40, interest and costs.
In March 2017, Hua Rong applied for and obtained leave to enforce the Adjudication Determination, and judgment in terms of the same.
On 4 April 2017, Civil Tech applied to court to set aside the Adjudication Determination, and the order of court granting Hua Rong leave to enforce the Adjudication Determination and judgment in terms of the same. In gist, Civil Tech argued that the respondent to a payment claim under the Act is entitled to raise any claim or set-off to withhold payment, as long as the payment response makes mention of that claim or set-off. The Adjudicator had thus erred in refusing to consider the set-off that Civil Tech had raised based on the C933 Contract. This was a jurisdictional error, and the Adjudication Determination should therefore be set aside.
The decision below After hearing Civil Tech’s application on 15 and 30 May 2017, the Judge dismissed the application on 24 July 2017 in
The Judge began his analysis by stating the purpose of the Act, drawing on our judgment in
The Judge then turned to the provisions of the Act and the Building and Construction Industry Security of Payment Regulations (Cap 30B, Rg 1, 2006 Rev Ed) (“the Regulations”). He noted that in
The Judge proceeded to analyse ss 15(3) and 17(3) of the Act, which he considered “especially germane” to the issue before him (Judgment at [8]). The Judge noted that both these provisions used the singular articles, referring to “a” or “the” contract (Judgment at [34]). The Judge held on this basis that the language of ss 15(3) and 17(3) supported the Single Contract Interpretation.
The Judge then reasoned that “a convincing reason of policy” supported the Single Contract Interpretation (Judgment at [35]). If respondents to payment claims could rely on withholding reasons that did not arise out of the Payment Claim Contract, adjudications would become prolonged and complicated because the merits of those reasons would have to be investigated and determined. The cost of an adjudication and the time needed to complete the same would be increased. That could not have been Parliament’s intention. Civil Tech’s interpretation of the law would “cut against the statute’s purpose of offering a contained and expedited means of giving temporary finality to payment disputes” (Judgment at [39]). The Judge also opined that permitting the respondent to a payment claim to raise any claim or set-off that was raised in the payment response as a withholding reason was not realistic, given two features of SOPA adjudications: strict timelines had to be adhered to, and not all adjudicators were legally trained (Judgment at [38]–[39]).
The Judge concluded that the text of the Act and the Regulations, and their underlying object and purpose, required the court to adopt the Single Contract Interpretation (Judgment at [40]). The Judge then considered and rejected Civil Tech’s arguments against the Single Contract Interpretation. In particular, the Judge addressed Civil Tech’s submission that respondents to payment claims in some foreign jurisdictions had been held to be entitled to withhold payment, under security of payment legislation similar to the Act, on the basis of a claim arising from a contract other than the Payment Claim Contract (a “Cross-Contract Claim”). The Judge examined the authorities cited by Civil Tech and found that there was no clear case where a foreign court had held that Cross-Contract Claims could constitute valid grounds for withholding payment. Rather, it seemed that the legislative and judicial attitude in foreign jurisdictions was one of suspicion towards Cross-Contract Claims (Judgment at [61]–[62]).
The Judge then held that the Adjudicator did not breach s 17(3)(
To continue reading
Request your trial-
Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd
...Pte Ltd v United Integrated Services Pte Ltd [2020] 1 SLR 206 at [50], citing Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [2018] 1 SLR 584 at [23]–[32]. It is not surprising to see that this is not the first occasion on which this conundrum has been in issue before the Singapore court......
-
Harmonious Coretrades Pte Ltd v United Integrated Services Pte Ltd
...to a construction contract should “pay now, argue later” (at [20]). More recently in Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [2018] 1 SLR 584 (“Hua Rong”), this court had the opportunity to consider which of two competing conceptions of cash flow the SOPA aimed to promote. It was ......
-
Comfort Management Pte Ltd v OGSP Engineering Pte Ltd
...Citiwall Safety Glass Pte Ltd v Mansource Interior Pte Ltd [2015] 1 SLR 797 (folld) Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [2018] 1 SLR 584 (refd) Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd [2005] NSWCA 228 (refd) Grouteam Pte Ltd v UES Holdings Pte Ltd [2......
-
SH Design & Build Pte Ltd v BD Cranetech Pte Ltd
...Amount cannot be regarded as a cross-contract set-off. The Court of Appeal in Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [2018] 1 SLR 584 (“Hua Rong (CA)”) made it clear that each adjudication under the SOP Act should relate only to the contract upon which the payment claim is founde......
-
Building and Construction Law
...Engineering Pte Ltd [2018] 1 SLR 979 at [97]. 108 Comfort Management Pte Ltd v OGSP Engineering Pte Ltd [2018] 1 SLR 979 at [102]. 109 [2018] 1 SLR 584. 110 Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [2018] 1 SLR 584 at [56(a)]. 111 Civil Tech Pte Ltd v Hua Rong Engineering Pte Ltd [......