Chua Tian Chu and another v Chin Bay Ching and another
Jurisdiction | Singapore |
Judge | Andrew Ang J |
Judgment Date | 20 May 2011 |
Neutral Citation | [2011] SGHC 126 |
Court | High Court (Singapore) |
Docket Number | Suit No 778 of 2009 |
Published date | 27 May 2011 |
Year | 2011 |
Hearing Date | 12 November 2010,08 November 2010,19 November 2010,10 November 2010,16 November 2010,18 November 2010,12 January 2011,22 November 2010,09 November 2010,11 November 2010,15 November 2010 |
Plaintiff Counsel | Adrian Ee (Ramdas & Wong) |
Defendant Counsel | Ramalingam Kasi (Raj Kumar & Rama) andCollin Choo (Derrick Wong & Lim BC LLP) |
Subject Matter | Building and Construction Law,Damages,Liquidated Damages |
Citation | [2011] SGHC 126 |
The plaintiffs, Mr Chua Tian Chu (“Mr Chua”) and Ms Cheang Poh Ling Pauline, were the purchasers of a property located at 22A Kheam Hock Road, Singapore (“the property”), pursuant to a sale and purchase agreement (“the Agreement”) entered into with the defendants, Mr Chin Bay Ching (“Mr Chin”) and Ms Tjia Mui Kui on 30 November 2006. The defendants were the vendors as well as the developers of the property. The agreed purchase price of the property was $5,680,000.
Prior to the sale of the property to the plaintiffs, Mr Chin had intended to renovate the detached bungalow standing on the land, built sometime in the late 1980s or early 1990s. Mr Chin engaged the services of an architectural firm by the name of Formwerkz Architects (“FA”) and a main contractor, Kian Hong Seng Construction Pte Ltd (“KHSC”), to carry out re-construction works on the property. Upon submission of the original building layout plans (“BP01”) drawn up with the assistance of FA, Mr Chin obtained the Building and Construction Authority’s (“BCA”) approval on 21 August 2006.
Shortly thereafter, in or around November 2006, the plaintiffs began negotiations with the defendants to purchase the property. The negotiations were principally in relation to BP01 (the original building layout plans designed by FA) and resulted in a list of amendments thereto to be incorporated into the Agreement. The finalised list of amendments was incorporated by way of the Fourth and Fifth Schedules annexed to the Agreement. While the Fourth Schedule consolidated the plaintiffs’ amendments to BP01, the Fifth Schedule predominantly related to renovation works as well as additional fixtures and fittings to be integrated into the property. Additional changes were made to the Fifth Schedule on 4 December 2006, after the Agreement was signed and an amended list replaced the Fifth Schedule originally attached to the Agreement.
By 26 January 2007, a revised building layout plan (“BP02”) had been drawn up. The defendants submitted the second application for BCA’s approval in July 2007 which was subsequently approved on 7 September 2007. It is worthwhile noting that FA also prepared three other building layout plans on 1 February 2007, 23 October 2007 and 16 July 2008.
Clause 9.1 of the Agreement imposed a contractually stipulated deadline for the delivery of the notice to take vacant possession of the property as “not later than 31
The Vendor
shall deliver vacant possession of the Property to the Purchaser bydelivering a notice to the Purchaser to Take Possession in respect of the Property.On delivery of vacant possession of the Property to the Purchaser, the Vendormust deliver to the Purchaser or his solicitorsa copy of the Temporary Occupation Permit for the Property togetherwith the certificate from the Vendor’s architect that the building, drainage, sewerage and electrical works serving the Property have been constructed in accordance with the plans and specifications approved by the Building Authority and that water and electricity supplies have been duly connected to the Property. [emphasis added]
On 6 January 2009, more than a year after the contractually stipulated date, the defendants gave notice to the plaintiffs to take vacant possession of the property following BCA’s issuance of the temporary occupation permit (“TOP”) on 6 January 2009. The plaintiffs took the position that the defendants’ notice to take vacant possession was only valid upon delivery of a copy of the TOP,
Clause 4 of the Agreement set out the payment schedule agreed by the parties for the progress instalment payments of the purchase price. As at 15 January 2009, the plaintiffs had completed the payment of 20% of the purchase price in accordance with the time line set out in cll 4.1.1, 4.1.2 and 4.1.3. Under cl 4.1.4 of the Agreement, a further 70% was payable “
On
Clauses 12.1 and 4.1.5 of the Agreement provided as follows:
On
The plaintiffs withheld payment of the $418,000 due under cl 4.1.5(a) on the basis that the property was not fit for occupation. They demanded that rectification works be conducted immediately by the defendants. The defendants were informed by the plaintiffs’ solicitors to complete all the outstanding works identified in a list prepared by Mr Chua dated 30 January 2009. Furthermore, the plaintiffs gave the defendants one month’s notice, expiring on 6 March 2009, to put the property in a state fit for occupation.
Clause 6.1 of the Agreement provided:
In addition to the charge of interests under
Clause 5 , the Vendor is entitled to give the Purchaser a not less than 21 days notice to pay any sum that remains unpaid for a period of 14 days or more after the due date of payment, or to comply with any or all terms or conditions of this Agreement, failing which the Vendor may at its own election (i) deem that the Purchaser is in breach and (ii) further deem that the Purchaser has repudiated this Agreement. [emphasis in original]
On 4 March 2009, the defendants served 21 days’ notice on the plaintiffs under cl 6.1 of the Agreement demanding payment of the sum of $418,000 overdue under cl 4.1.5(a). The plaintiffs’ repeated failure to complete the sale and purchase of the property, notwithstanding multiple extensions arranged between the parties, culminated in the defendants’ rescission of the Agreement on
The plaintiffs commenced this action by way of writ on
To continue reading
Request your trial-
Ng Koon Yee Mickey v Mah Sau Cheong
...if they were not able to reach an agreement on these two points: at [140] and [141]. [Observation: In Chua Tian Chu v Chin Bay Ching[2011] SGHC 126 (“Chua Tian Chu”), the High Court opined that the prevention principle afforded an “equitable remedy”. However, apart from Chua Tian Chu and Fu......
-
Ng Koon Yee Mickey v Mah Sau Cheong
...of an act of prevention adopted in Yap Boon Keng Sonny was thereafter applied in Chua Tian Chu and another v Chin Bay Ching and another [2011] SGHC 126 (“Chua Tian Chu”) (at [62]). Andrew Ang J considered that when an employer or a purchaser had performed acts of prevention, in the absence ......
-
Fundamental Investors Pte Ltd v Palm Tree Investment Group Pte Ltd
...of the Loan was “set at large” due to the prevention principle endorsed in Chua Tian Chu and another v Chin Bay Ching and another [2011] SGHC 126 (“Chua Tian Chu”).46 Issues to be determined Based on the foregoing, the key issues to be determined are as follows: Whether the key documents on......
-
Ajit Chandrasekar Prabhu and another v Yap Beng Kooi and another
...the enjoyment of the right of possession of a substantial part of the property. Similarly, in Chua Tian Chu v Chin Bay Ching and another [2011] SGHC 126 (at [45]), it was stated, citing Topfell Ltd v Galley Properties Ltd [1979] 1 WLR 446 (“Topfell”), that vacant possession means “a state i......
-
The legal and commercial frameworks
...Ltd [2001] EWCA Civ 1377 at [16], per Dyson LJ. Another expression is “quasi-construction contract”: Chua Tian Chu v Chin Bay Ching [2011] SGHC 126 at [66], per Andrew Ang J. 235 Robinson v PE Jones (Contractors) Ltd [2010] EWHC 102 (TCC) at [77]–[78], per HHJ Stephen Davies (airmed [2012] ......
-
Statutory regulation of work
...for occupation: Building Control Act (Cap 29, 1999 revised edition) (Sing) section 12(4). See also Chua Tian Chu v Chin Bay Ching [2011] SGHC 126 at [48], per Andrew Ang J. 156 here are also speciic statutory licensing and registration regimes applicable to architects, and in Queensland to ......
-
Building and Construction Law
...1 SLR(R) 385 at [385]; Lim Chin San Contractors Pte Ltd v LW Infrastructure Pte Ltd [2011] 4 SLR 455; and Chua Tian Chu v Chin Bay Ching [2011] SGHC 126 at [58]–[64]. 65 GTMS Construction Pte Ltd v Ser Kim Koi [2021] SGHC 9 at [662], referring to Chow Kok Fong, Law and Practice of Construct......
-
Building and Construction Law
...of the termination, the stipulated date for completion under the Subcontract would cease to be effective (Chua Tian Chu v Chin Bay Ching[2011] SGHC 126 at [60]) and the defendant would lose its right to enforce the liquidated damages provision (Trollope & Colls Ltd v North West Metropolitan......