CEF and another v CEH
Jurisdiction | Singapore |
Judge | Sundaresh Menon CJ |
Judgment Date | 18 July 2022 |
Neutral Citation | [2022] SGCA 54 |
Court | Court of Appeal (Singapore) |
Docket Number | Civil Appeal No 153 of 2020 |
Published date | 21 July 2022 |
Year | 2022 |
Hearing Date | 26 January 2022 |
Plaintiff Counsel | Tan Chee Meng SC, Chou Sean Yu, Oh Sheng Loong Frank, Wong Zheng Hui Daryl and Seah Ying Ying (WongPartnership LLP) |
Defendant Counsel | Davinder Singh s/o Amar Singh SC, Fong Cheng Yee David, Hanspreet Singh Sachdev and Tanmanjit Singh (Davinder Singh Chambers LLC) |
Subject Matter | Arbitration,Award,Recourse against award,Setting aside |
Citation | [2022] SGCA 54 |
The parties to this appeal were once eagerly engaged in the enterprise of constructing and operating a steel-making plant. Unfortunately, disputes over the construction and production capabilities of the plant arose and the respondent terminated the construction contract. An arbitration proceeding ensued in which the respondent was largely successful. The appellants now raise before us, as they did in the court below, issues of breach of natural justice and, further, challenge the workability and enforceability of the award issued by the tribunal.
Apart from the first appellant, which is incorporated in Narnia, all the parties are companies incorporated in Ruritania. The first appellant is a multinational company which designs, builds, and sells plants for the iron and steel industry. It is the parent of the second appellant. In 2011, the appellants were contracted to design and build a steel-making plant for the respondent.
The respondent manufactures hot-rolled steelcoils and carries on business on the premises of its parent, a major steelmaker in Ruritania (the “Parent”).
The relationship between the parties broke down in 2016 and each started action against the other. This led to a consolidated arbitration (the “Arbitration”) in October 2016. An award was issued in 2019 (the “Award”) and various orders made in favour of the respondent.
The appellants were dissatisfied with the Award and therefore applied to the Singapore High Court to set it aside. They asserted breach of natural justice under s 24(
In June 2011, the first appellant entered into a contract (the “Contract”) with the Parent. Under the Contract, the first appellant was to provide engineering equipment and services to design and build a steel-making plant (the “Plant”) on a site in Ruritania (the “Site”) owned by the Parent for a contract price of F$92.7m (“F$” being a pseudonym for the currency used in the contract documents). The material terms of the Contract were as follows:
In September 2011, the Parent assigned its rights, title, interest and liabilities under the Contract to the respondent. However, the Parent continued to retain ownership of the Site.
In March 2014, the first appellant supplied the respondent with additional equipment worth F$49,000 and additional services worth approximately F$31,000. This equipment was subsequently used in or incorporated into the Plant. The appellants received no compensation from the respondent for providing these additional services and equipment.
About two months later, in May 2014, the appellants and the respondent entered into a service agreement (“Service Agreement”) whereunder the first appellant assigned to the second appellant the first appellant’s obligation under the Contact to provide supervision and training services to the respondent.
The parties’ dispute and the ArbitrationUnfortunately, there were delays in the construction of the Plant and the completed Plant never achieved its production target. The respondent purported to terminate the Contract. So, in August 2016, the appellants commenced an arbitration against the respondent. Some three weeks later, the respondent commenced its own arbitration against the appellants. In October 2016, the two arbitrations were consolidated into the Arbitration by consent. The claimants and respondent in the Arbitration were the appellants and the respondent, respectively. By November 2016, the Tribunal was constituted comprising Dr Michael Moser (President of the Tribunal), Prof Mauro Bussani and Mr Alan J Thambiayah.
The Arbitration was commenced under both the Contract and the Service Agreement. Art 26.1 of the Contract provided that it was governed by Singapore law, while Art 26.2 of the Contract provided that any dispute arising from or in connection with the Contract was to be arbitrated in Singapore under the Rules of Arbitration of the International Chamber of Commerce (“ICC Rules”). Article 6.2 of the Service Agreement incorporated Art 26 of the Contract.
On 3 January 2017, in accordance with Art 23 of the ICC Rules, the parties and the Tribunal signed the terms of reference (“Terms of Reference”) setting out the parties’ claims in the Arbitration.
Based on the Terms of Reference, the reliefs sought by the appellants in the Arbitration included the following:
…
…
…
The respondent, for its part, stated in the Terms of Reference that it was seeking the following reliefs:
On 28 November 2019, the Tribunal issued the Award. The majority of the Tribunal found that the respondent had been induced to enter into the Contract by the appellants’ misrepresentations, and that the respondent was therefore entitled to rescission of both the Contract and the Service Agreement. The Tribunal made various orders including the following:
On 25 February 2020, the appellants applied to the High Court to set aside the Award.
Transfer Order The bulk of the appellants’ submissions before the Judge was directed at setting aside the Transfer Order. They submitted that:
To continue reading
Request your trial