Bintai Kindenko Pte Ltd v Samsung C&T Corp and another
Jurisdiction | Singapore |
Judge | Aedit Abdullah J |
Judgment Date | 03 September 2018 |
Neutral Citation | [2018] SGHC 191 |
Court | High Court (Singapore) |
Docket Number | Suit No 800 of 2017 (Summons No 4313 of 2017) |
Year | 2018 |
Published date | 04 June 2019 |
Hearing Date | 20 November 2017,01 December 2017,19 January 2018 |
Plaintiff Counsel | Josephine Choo Poh Hua, Lee Hui Min and Dynyse Loh Jia Wen (WongPartnership LLP) |
Defendant Counsel | Kelvin Aw Wei Keng, Lee Kok Wee, Eugene and Leonard Chew Wei Chong (Morgan Lewis Stamford LLC),second defendant not represented, not present. |
Citation | [2018] SGHC 191 |
This case concerns an interim injunction restraining the 2nd defendant from paying out on a banker’s guarantee issued in favour of the 1st defendant and to prevent the 1st defendant from receiving payment of the same. The banker’s guarantee was procured by the plaintiff pursuant to its obligation under the subcontract with the 1st defendant. Following alleged breaches of the subcontract between the plaintiff and the 1st defendant, the latter called on the guarantee on 28 August 2017. Subsequently, on 29 August 2017, the plaintiff sought and obtained an interim injunction against the demand and payment on an
As the matter is presently at the interim stage and given the existence of multiple contractual documents, I would refer to the general contractual arrangement between the plaintiff and 1st defendant as the “subcontract” and leave specific references to documents where necessary.
The genesis of the present application stems from a subcontract entered into by the 1st defendant and the plaintiff for the supply and installation of mechanical, electrical and plumbing works in December 2012; the plaintiff being the subcontractor. A banker’s guarantee of about $4.3m, issued by the 2nd defendant-bank, was granted in favour of the 1st defendant pursuant to the subcontract. After certain delays and alleged contractual breaches, the 1st defendant imposed liquidated damages and sought to call on the guarantee. The circumstances leading up to that demand are as follows.
The completion dates for the various phases of the works to be done spanned March 2013 to April 2014. The plaintiff, however, only achieved actual completion of the last phase in February 2015. Thereafter, various letters were exchanged from the period of May 2015 to January 2016, where the 1st defendant sought to pin responsibility for the delay on the plaintiff and notified the plaintiff of potential liquidated damages to be paid.
Payment claims filed by the plaintiff, and responses from the 1st defendant detailing reasons for withholding payments and indicating liquidated damages payable by the plaintiff were then exchanged between February 2017 and July 2017. Notably, the 1st defendant addressed the plaintiff’s request for the release of the first half of retention monies, variation order claims and back charges in the responses.
On 7 July 2017, the plaintiff lodged an adjudication application against the 1st defendant in relation to the first half of the retention monies. An adjudicator was appointed on 11 July 2017. Further payment claims and responses continued to be filed after the appointment of the adjudicator. The adjudication determination was granted on 15 August 2017 in favour of the plaintiff; no determination was made on the variation order claims and back charges. Shortly after, the plaintiff requested for payment of the amount due under the adjudication determination. The 1st defendant replied with a payment response on 24 August 2017 explaining why payments were withheld.
On 28 August 2017, the 1st defendant made a demand on the banker’s guarantee on the basis that the plaintiff owed it liquidated damages. Due to the urgency of the matter, the plaintiff applied for, and obtained, an interim injunction restraining the 1st defendant’s call on the guarantee on 29 August 2017. This interim injunction was then discharged following an
At issue between the parties were the circumstances of the
For completeness, the 1st defendant eventually filed an application to set aside the adjudication determination. The matter was heard on 14 November 2017 by Foo Chee Hock JC. The judge found that the adjudication determination was made in breach of natural justice as it failed to take into account other essential issues of back charges for scaffolding and re-assessed variation works, and consequently set aside the adjudication determination. The matter was thereafter appealed by the plaintiff. The appeal was dismissed in
The plaintiff’s interim injunction application was on the basis that it would be unconscionable, in the circumstances, for the 1st defendant to have called on the guarantee. The 1st defendant argued that the plaintiff’s application was fundamentally flawed as the ground of unconscionability was not available to the plaintiff in the first place. The subcontract incorporates a clause which expressly stipulates that except in the case of fraud, the plaintiff shall not for any reason whatsoever be entitled to enjoin or restrain the 1st defendant on making any call or demand on the guarantee (“Exclusion Clause”). Such a clause was upheld in
In any event, the subcontract contained an arbitration clause. The parties expressly agreed to refer disputes relating to a demand on the guarantee to arbitration.
There were also material facts not disclosed to the court. An applicant in an
Additionally, the
If there was to be any challenge to the call on the guarantee, the only ground available was fraud. There was not even a shred of an allegation of fraud in the supporting affidavits, nor was this raised to the court in argument. In any event, fraud cannot be made out:
In the present application, the plaintiff has sought to change their position from unconscionability to fraud. The 1st defendant is surprised by the fraud...
To continue reading
Request your trial-
Bintai Kindenko Pte Ltd v Samsung C&T Corp and another
...a call on a banker’s guarantee. The Judge’s grounds of decision can be found at Bintai Kindenko Pte Ltd v Samsung C&T Corp and another [2018] SGHC 191 (“the GD”). We dismissed the appeal after hearing the appellant and the first respondent on 1 April 2019. The Second Respondent, DBS Bank Lt......