Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd
Jurisdiction | Singapore |
Judge | Chan Seng Onn J |
Judgment Date | 30 November 2015 |
Neutral Citation | [2015] SGHC 307 |
Year | 2015 |
Date | 30 November 2015 |
Published date | 19 April 2017 |
Hearing Date | 29 May 2015,30 July 2015,08 July 2014,05 August 2015,20 March 2015,17 July 2014,29 July 2015,17 March 2015,10 July 2014,31 July 2015,18 March 2015,27 May 2015,04 August 2015,19 March 2015,06 August 2015,28 May 2015,16 July 2014,15 October 2015,09 July 2014,15 July 2014 |
Plaintiff Counsel | Tan Chuan Thye SC, Avinash Pradhan, Alyssa Leong and Arthi Anbalagan (Rajah & Tann Singapore LLP) |
Citation | [2015] SGHC 307 |
Defendant Counsel | Daniel John and Kevin Cheng (Goodwins Law Corporation) |
Court | High Court (Singapore) |
Docket Number | Suit No 219 of 2013 |
The Plaintiff is a company incorporated in the Special Administrative Region of the People’s Republic of China, Hong Kong. The Defendant is a company incorporated in Singapore and is an established supplier, designer and manufacturer of heavy machinery (including tensioners and winches) for offshore use in the marine and oil and gas industry.
In 2007, the Plaintiff purchased a 300 tons reel drive unit (“RDU”) from the Defendant. Attached below is a photograph of the RDU that was fabricated by the Defendant. The photograph shows a 300 tons reel (brown in colour) sandwiched between the two towers of the RDU (blue in colour) mounted on skids (blue in colour) on the deck at the aft of the ship, the “Maersk Responder”.
For a better understanding of the overall structure of the RDU, I have also attached below a colour schematic diagram of the RDU.
The RDU was delivered to the Plaintiff on 10 April 2008 and thereafter mounted on board the “Maersk Responder” for the laying of undersea umbilical for Nexus Energy at the Longtom field in the Bass Straits of Australia. After having laid one complete reel of umbilical and in the course of laying the second reel, a major failure of one of the gearbox assemblies occurred. The hydraulic drive motor and gear assembly on one of the towers of the RDU (
In this action, the Plaintiff claims that the RDU already suffered from manufacturing and design defects at the time of delivery. Broadly, these defects pertain to the following:
The parties have agreed that the court is to determine this claim under Singapore law notwithstanding the choice of Western Australian law in cl 21 of the Sale and Purchase Agreement (“Sale and Purchase Agreement”) for the RDU.
As the trial progressed and with fresh evidence emerging, the parties felt that amendments to their pleadings were needed. Instead of piecemeal amendments, the parties waited until the completion of the trial to consolidate all their intended amendments and attached them to their closing submissions. I think this is an efficient and cost-effective approach. No party has been prejudiced as the parties were clearly aware from the beginning of the trial what the main issues and areas of dispute were and they were not taken by surprise. Accordingly, I grant them leave to amend their pleadings.
After a technically challenging trial over several days where 17 factual witnesses testified and seven expert witnesses from different fields of engineering gave their expert opinion as a group in a “hot-tub” instead of sequentially, and after having carefully considered all the relevant evidence and the detailed and comprehensive submissions from both parties, I find on a balance of probabilities, for the reasons stated in this judgment based on the pleadings as amended, the facts that I have found and the totality of the factors that I have evaluated and taken into consideration, that the RDU:
For ease of reference, I have attached at Appendix 1 a “Glossary of Witnesses” with a brief summary of the focus of their evidence at the trial. In the course of this judgment, I shall refer to the evidence of some of these witnesses.
Sale and Purchase AgreementIt is not disputed that the Defendant was aware that the RDU was purchased by the Plaintiff specifically for lease to Trident Offshore Services (“Trident”) for the laying of undersea umbilical in the Bass Straits of Australia for Nexus Energy in the Longtom Project.
The Plaintiff and Defendant entered into the Sale and Purchase Agreement dated 7 September 2007 which provides,
When it transpired that ABS does not provide certification for machinery such as the RDU, the Defendant suggested in an email dated 12 October 2007 that ABSG Consulting Inc (“ABSG”), an entity related to ABS, carry out the “
It is not disputed that the Defendant was solely responsible for designing the entire RDU although this obligation was not expressly stated in the Sale and Purchase Agreement. In fact, the Defendant’s Confidential Bundle of Documents (“Confidential Bundle”), containing
After the Defendant had designed and fabricated the RDU, a factory acceptance test (“FAT”) was carried out and signed off by Mr Terry Griffiths on behalf of the Plaintiff on 26 February 2008 and counter-signed by Mr Chong, the then ABSG surveyor with ABSG, and Mr Steven Gan, the Assistant Manager-After Sales of the Defendant. ABSG issued certificates for the design reviews it carried out, as well as the manufacturing processes and the FAT.
Inadequate design of the RDUI will deal with the design inadequacies first and there are several alleged by the Plaintiff. I will address them seriatim.
Failure to take the vessel roll into account The Plaintiff submits that the Defendant failed to take vessel roll into account in the RDU design. It is not disputed that the inertial forces arising out of the vessel’s accelerations must form part of the design considerations for the RDU. The input design parameters for any computer program (
I accept the explanation of Dr Yang Ting that there are basically two acceptable methods of specifying such input design parameters for the
In either case, those equivalent accelerations arising from the vessel’s motions can be used for computing the
But if in either case the maximum roll angle of the vessel for example is expected to be large, then the weight of the equipment itself (which is a gravitational force and not an inertial force) must be resolved into the X and Y components because of the large roll angle and then
To continue reading
Request your trial-
PH Hydraulics & Engineering Pte Ltd v Airtrust (Hong Kong) Ltd
...payable by PH to Airtrust. The High Court judge (“the Judge”) held, in Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd [2015] SGHC 307 (reported in part in [2016] 1 SLR 1060) (“the Judgment”), in favour of Airtrust on Issue 1 and proceeded to find that PH’s conduct merited th......
-
Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd
...and purchase agreement between the parties. The judgment is reported as Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd [2016] 1 SLR 1060 (“the Judgment”). The plaintiff sought to recover costs on an indemnity basis, arguing that the defendant’s conduct of the case was so mor......
-
Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd
...and purchase agreement between the parties. The judgment is reported as Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd [2016] 1 SLR 1060 (“the Judgment”). The plaintiff sought to recover costs on an indemnity basis, arguing that the defendant’s conduct of the case was so mor......
-
Telemedia Pacific Group Ltd v Yuanta Asset Management International Ltd
...on 10 February 2011 to give such an instruction. The parties relied upon Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd [2016] 1 SLR 1060 (“Airtrust”) in support of their respective contentions regarding punitive damages. I note that an appeal against the High Court’s decisi......
-
Contract Law
...in contract law … [though the question is] still an open one’. 12.193 In Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd[2016] 1 SLR 1060 (‘Airtrust’), Chan Seng Onn J took the view that Singapore courts have the power to award punitive damages for breach of contract. 12.194 ......
-
Contract Law
...Holdings Ltd v Yang Shushan [2016] 3 SLR 193 at [217]. 191 [2007] EWCA Civ 286; [2008] 1 All ER 74 at [59]. 192 [2017] 3 SLR 47. 193 [2016] 1 SLR 1060. 194 Airtrust (Hong Kong) Ltd v PH Hydraulics & Engineering Pte Ltd [2016] 1 SLR 1060 at [264]; see also (2015) 16 SAL Ann Rev 307 at 367–37......
-
Contract Law
...Thomson Medical Pte Ltd [2017] 1 SLR 918 at [10]. 135 ACB v Thomson Medical Pte Ltd [2015] 2 SLR 218 at [4]. 136 [2017] 2 SLR 129. 137 [2016] 1 SLR 1060; see also discussion in (2015) 16 SAL Ann Rev 307 at 367–372, paras 12.193–12.207. 138 As to which, the Court of Appeal has clarified in A......